Home › Calculators › Event planning › Run-of-Show Planner
Opens on Chapter 21’s first worked example: Arlo’s setup for Pearl’s lunch: doors at noon, set tables 45 minutes, decorate 30, food out 20 after the tables, two people, a 20-minute buffer.
How it works
Latest start = the fixed time − the jobs’ minutes − the buffer. When different people work at once, only the longest chain counts: that’s the critical path, and any job on it that slips delays everything. Jobs off it have slack, time they can slip without harm. Teardown: the jobs anyone can share divide among the helpers (round up); a last job that waits for the rest, like the sweep, takes its own time with the people it needs.
Numbers can be typed as 1,200, $45, 0.5, 3/4 or 1 1/2. Whole things (tables, packs, trays, bags, shifts) are rounded up, money to the cent. Everything stays in your browser: no sign-up, nothing stored or sent.