Work back from the fixed time; jobs done at once by different people overlap, so the longest chain (the critical path) decides; add a buffer.

Home › Calculators › Event planning › Run-of-Show Planner

Opens on Chapter 21’s first worked example: Arlo’s setup for Pearl’s lunch: doors at noon, set tables 45 minutes, decorate 30, food out 20 after the tables, two people, a 20-minute buffer.

The buffet line
Teardown
Enter your numbers, then press Work it out.

How it works

Latest start = the fixed time − the jobs’ minutes − the buffer. When different people work at once, only the longest chain counts: that’s the critical path, and any job on it that slips delays everything. Jobs off it have slack, time they can slip without harm. Teardown: the jobs anyone can share divide among the helpers (round up); a last job that waits for the rest, like the sweep, takes its own time with the people it needs.

From the book, Chapter 21. Alone, Arlo must start at 10:25 a.m. (10:05 a.m. with the buffer); with Junie decorating at the same time, 10:55 a.m. (10:35 a.m.). The wedding setup’s critical path is 210 minutes, done at 12:30 p.m.; the lights crew’s 140 minutes have 70 minutes of slack. Teardown, 277 person-minutes, ends at 10:57 p.m. with six helpers and 12:19 a.m. with two. Every chapter and its tool →

Numbers can be typed as 1,200, $45, 0.5, 3/4 or 1 1/2. Whole things (tables, packs, trays, bags, shifts) are rounded up, money to the cent. Everything stays in your browser: no sign-up, nothing stored or sent.